Wind Energy > Bas-Saint-Laurent Project The project -- Completed steps -Economic Benefits --Calendar Contact
Preliminary meetings with option holders
Preliminary meetings with Regional Municipal Counties (MRC) and municipalities
Notice of Application filed with the MDDEP
Project analyzed and environmental directive (nature, range, scope) transmitted by the MDDEP
Bidding submitted to Hydro-Québec
Sept. 2007
Bids analyzed by Hydro-Québec
Sept. 2007- May 2008
Bid selected
5 May 2008
Meeting with MRC and municipal elected officials
May-June 2008
Power purchase agreement signed
June 2008
Meetings with option holders
Spring-Summer 2008
Information Sessions - municipalities, MRCs and public
Environmental impact assessment completed by developer
Sept. 2008 - Sept. 2009
Public and municipalities consulted
MDDEP Admissibility Analysis
Quebec environmental public hearing board (BAPE)
MDDEP Environmental Assessment of the Project
Recommendations made by the Minister of Sustainable Development, the Environment and Parks (MDDEP) to Cabinet
Project Approval
MDDEP Order-in-Council pertaining to the project
Required approvals obtained:
Ooption contracts (private) come into force
Project implemented (construction phase)